NOTICE TO OCCUPANTS
ASBESTOS ABATEMENT PROJECT
TO: Teachers, Students, and Staff
FROM: Dr. Tom Mulligan, Superintendent
DATE: June 1, 2023
DEM Services, Inc. has been given permission to perform asbestos removal activities in the Arcola Elementary & High School, beginning on Monday, June 19, 2023.
The asbestos will be removed from the family consumer science room located in the original high school building. All areas affected by this project will be clearly marked and isolated with a visible barrier. Air quality both inside and outside the contained area for this project will be continually monitored.
Please do not enter the project area. If you have any questions regarding this matter, please see me as soon as possible.
Project dates are from June 19, 2023 to June 29, 2023.
Thank you for your cooperation.