NOTICE TO OCCUPANTS

ASBESTOS ABATEMENT PROJECT

 TO:       Teachers, Students, and Staff                                      

FROM:  Dr. Tom Mulligan, Superintendent

DATE:  June 16, 2023

Triple A Asbestos Services has been given permission to perform asbestos removal activities in the Arcola Elementary & High School, beginning on Monday, July 10, 2023.

The primary removal will be done in the high school locker rooms. All areas affected by this project will be clearly marked and isolated with a visible barrier. Air quality both inside and outside the contained area for this project will be continually monitored.

Please do not enter the project area. If you have any questions regarding this matter, please see me as soon as possible.

Project dates are from July 10, 2023 to July 20, 2023.